Answer:
4 more men should be engaged to finish the rest of the work in 10 days working 8 hours a day.
Step-by-step explanation:
No of men is inversely proportional to Number of hours worked
40× 12× 6 = x × 10 × 8
40 × 72=x × 80
2880 = 80x
x= 2880/80
x= 36
40 - 36 = 4