A Company Contracts To Paint 3 Houses. Mr. Brown Can Paint A House In 6 Days While Mr. Black Would Take 8 Days And Mr. Blue 12 Days. After 8 Days Mr. Brown Goes On Vacation And Mr. Black Begins To Work For A Period Of 6 Days. How Many Days Will It Take Mr. Blue To Complete The Contract? 7 8 11 O 12​

Answers 2

Answer:

12

Step-by-step explanation:

this is the answer hope you like it

Answer:

11

Step-by-step explanation:

A company contracts to paint 3 houses. Mr. Brown can paint a house in 6 days while Mr. Black would take 8 days and Mr. Blue 12 days. After 8 days Mr. Brown goes on vacation and Mr. Black begins to work for a period of 6 days. How many days will it take Mr. Blue to complete the contract?

A. 7

B. 8

C. 11

D. 12

ANSWE = C

IF YOU LIKE THIS ANSWER

SO PLEASE MARK MY ANSWER AS BRAINLIEST

THANKS AND REGARDS

- BRAK FF YT

If you know the answer add it here!

Can't find the answer?

Log in with Google

or

Forgot your password?

I don't have an account, and I want to Register

Choose a language and a region
How much to ban the user?
1 hour 1 day 100 years