the scrum development team is getting ready to start their agile execution. in the current release, 8 sprints have been planned. the team wants to give the product owner, a picture of what are they planning to do in the current release. to start this, they need to decide on the goal of each sprint. when are the sprint goals identified?

Answers 1

Answer:

Option - d

Explanation:

Once before Sprint 1 and another one before Sprint 5